Program Overview
Federal National Priority List (NPL) Site Map
The Federal Superfund and Construction Bureau consults with Environmental Protection Agency (EPA) Region 8 on National Priorities List (NPL) sites and is typically the support agency overseeing the implementation of the remedial process. We provide technical and management assistance to EPA to support the remedial actions and agency decisions at NPL sites and work cooperatively with all other agency partners, local stakeholders and the public to keep them informed during the Superfund process. Montana DEQ’s activities are usually funded through cooperative agreements with EPA or settlement funds.
Federal Superfund Contacts
Main Number
(406) 444-6444
DEQ Program Support
Joann Wiggins (406) 444-6795
DEQ Federal Superfund Supervisor
Kevin Stone (406) 444-0214
List of Sites
The following is a list of sites that the Federal Superfund and Construction Bureau is currently working on. The final column is the Project Manager contact information for Montana DEQ Remediation. The Project Manager oversees the work being done alongside the EPA. The second table contains information about the Black Pine Mining Site, the Stimson-Bonner Mill Site, and the Upper Blackfoot Mining Complex, all of which are non-NPL sites but are under the Construction portion of the Bureau.
Site Name | Short Name | Site Location | CERCLA/ EPA ID | Lead | DEQ Project Manager | |
---|---|---|---|---|---|---|
ACM Smelter & Refinery NPC | ACMSRNPC | Great Falls | MTD093291599 | EPA | Dick Sloan | |
Anaconda Smelter Site | ACSS | Anaconda | MTD093291656 | EPA | Amber Nichols | |
Barker Hughesville Mining District | BHMD | Monarch | MTD612230748 | EPA | Amber Nichols | |
Basin Creek Mine | BCM | Basin | MTD982572562 | MT DEQ | Logan Dudding | |
Basin Mining Area | BMA | Basin | MTD982572562 | EPA | Dick Sloan | |
Billings PCE | BPCE | Billings | Proposed-NPL Site | EPA | Breana Pabst | |
Blacktail Creek | BTC | Butte | MTD980502777 | MT DEQ | Vacant | |
Burlington Northern Somers | BNS | Somers | Non-NPL Site | EPA | Dick Sloan | |
Butte Mine Flooding | BMF | Butte | MTD980502777 | EPA | Daryl Reed | |
Butte Priority Soils | BPS | Butte | MTD980502777 | EPA | Daryl Reed | |
Carpenter-Snow Creek Mining District | CSCMD | Neihart | MT0001096353 | EPA | Amber Nichols | |
Clark Fork River | CFR | Opportunity to Milltown | MTD980717565 | MT DEQ | Logan Dudding | |
Columbia Falls Aluminum Reduction Plant | CFAC | Columbia Falls | MTD057561763 | EPA | Dick Sloan | |
East Helena Smelter Site | EHS | East Helena | MTD006230346 | EPA | Daryl Reed | |
Flat Creek IMM Site | FCIMM | Superior | MT0012694970 | EPA | Daryl Reed | |
Frenchtown Mill (Smurfitt Stone) | Missoula | Pre-Listing | EPA | Breana Pabst | ||
Idaho Pole Co. | IDPC | Bozeman | MTD006232276 | EPA | Breana Pabst | |
Libby Asbestos | LA | Libby | MTD009083840 | EPA | Melody Wunderlin | |
Libby Ground Water Contamination | LGWC | Libby | MTD980502736 | EPA | Melody Wunderlin | |
Lockwood Solvent Groundwater Plume Site | LSGWP | Billings | MT0007623052 | EPA | Dick Sloan | |
Milltown Reservoir Sediments | MRS | Milltown | MTD980717565 | EPA | Breana Pabst | |
Montana Pole and Treating Plant | MTPOLE | Butte | MTD006230635 | MT DEQ | Jacob Wheeling | |
Mouat Industries | MI | Columbus | MTD021997689 | EPA | Daryl Reed | |
Rocker | ROCKER | Rocker | MTD980502777 | EPA | Daryl Reed | |
Silver Bow Creek/Butte Area Stream Side Tailings | SST | Butte-Anaconda | MTD980502777 | MT DEQ | Logan Dudding | |
Upper Tenmile Creek Mining Area | UTCMA | Helena, Rimini | MTSFN7578012 | EPA | Dick Sloan | |
Warm Springs Ponds | WSP | Warm Springs | MTD980502777 | EPA | Daryl Reed |
Non-NPL Construction Sites
Project Site Name | Short Name | Site Location | Program | MT DEQ Lead | Partners | FSB Project Manager |
---|---|---|---|---|---|---|
Black Pine Mine | BPM | Philipsburg | Construction Services | MT DEQ | USFS | Bob Flesher |
Stimson-Bonner Mill PCB Site | SBM | Bonner | State Superfund | MT DEQ | EPA/MT NRD | Vacant |
Upper Blackfoot Mining Complex | UBMC or Mike Horse | Lincoln | State Superfund | MT DEQ | USFS/MT NRD | Amber Nichols |
Specific Project Information
Blacktail Creek
Blacktail Creek is an urban stream located within Butte, MT. The creek originates in the Summit Valley, drains the Highland Mountains, and is a tributary to Silver Bow Creek. Blacktail Creek, along with the confluence with Silver Bow Creek, has been impacted by past industrial activities that disposed of mining, milling, smelting, and other wastes in the creek corridor. These depositions have led to an increased risk to human and environmental health.
With the signing of the amended record of decision for Butte Priority Soils Operable Unit, and the finalization of the enacting Consent Decree, the Montana Department of Environmental Quality, on behalf of the State of Montana, was assigned responsibility for implementing the BTC Riparian Actions and received a settlement of $20.5 million to successfully complete this project.
The major objectives of the remedial activities for the Blacktail Creek area, as outlined by the Consent Decree, are to:
- Remove tailings, wastes, contaminated soils and sediments from Blacktail Creek and Silver Bow Creek below the confluence with Blacktail Creek, including the Blacktail Creek wetlands;
- Control of discharge of contaminated groundwater to surface water in the project area (a responsibility of the settling defendants);
- Reconstruct Blacktail Creek and Silver Bow Creek Below the Confluence with Blacktail Creek;
- Revegetate all areas addressed in these actions in accordance with ARARs.
Currently, DEQ is in the pre-design investigation phase of the project. DEQ is working to investigate data gaps so that the project can move forward with the remedial design process. Making sure we have all the necessary data prior to moving forward with a design is a key step that ensures a science driven and cost-effective approach to meeting DEQ’s responsibilities in the Consent Decree.
Click to subscribe for email updates for the Blacktail Creek site: Email Updates
Draft Blacktail Creek UFP QAPP
Consent Decree
Butte Priority Soils Consent Decree Appendix D BPSOU Statement of Work
Butte Priority Soils Consent Decree Appendix H Blacktail Creek Riparian Actions Outline
Past Studies
MBMG Stream Characterization of Blacktail and Silver Bow Creeks
Data Gap Investigation – Silver Bow Creek and Blacktail Creek Corridors
Fact Sheets
Billings PCE
BPCE Vapor Intrusion (VI) Study Area is a shallow groundwater contaminant plume encompassing 855 acres and extends from the intersection of Industrial Avenue and Daniel Street in Billings, MT approximately three miles, east-northeast, through numerous mixed-use neighborhoods into downtown Billings. Contaminated groundwater is associated with releases of dry-cleaning chemicals and other industrial sources. The BPCE Site was added to the National Priorities List in the Federal Register in September 2021.
Multiple investigations and remedial actions have been conducted across the BPCE VI Study Area to assess groundwater quality and VI into structures above the COPC plume and are summarized below:
- 1993 – Montana Department of Environmental Quality (MDEQ) completed a preliminary assessment in which the MDEQ and EPA issued a “no further action” determination for the BPCE VI Study Area, given that the aquifer was not being used as a drinking water source at the time.
- 2001 – the MDEQ completed a site investigation and determined indoor air contaminant concentrations may exceed levels with the potential to cause health risks for building occupants (at structures overlying the groundwater plume).
- 2007 – EPA conducted a removal action involving the excavation and disposal of contaminated soil, injecting chemicals into groundwater to assist in the reduction of contamination, installing a non‑permeable barrier wall around the most contaminated groundwater, and installing vapor mitigation systems at seven structures overlying the plume.
- 2019 – MDEQ issued a RI Report that characterized the nature and extent of potential contaminates dissolved in groundwater known at the time. Multiple sources of potential contaminate were found. Surface and subsurface soil were determined to be leaching to groundwater and the VI pathway is complete at some structures.
- 2022 – EPA conducted a VI investigation including sampling of indoor air, crawlspace air, outdoor air, sub-slab vapor, and soil vapor in 48 structures in and near the BPCE VI Study Area.
- 2022 – EPA conducted a soil vapor and groundwater investigation including the installation and sampling of up to 103 temporary soil vapor points and 16 semi-permanent soil vapor points and sampling of 12 groundwater monitoring wells.
- 2022 – EPA conducted a utility corridor investigation including the sampling of 35 sanitary sewer manholes.
- 2022 – EPA conducted a VI investigation including sampling indoor air, crawlspace air, and sub-slab vapor in 112 structures.
- 2022 – EPA conducted a utility corridor investigation including the sampling of up to 58 sanitary sewer manholes.
Fact Sheet
Wondering whether your property is located within or near the Billings PCE study area? Use this web link to find out. https://arcg.is/0KyfvL1
Breana Pabst | DEQ Project Manager | Breana.Pabst@mt.gov | (406) 444-0215 |
Vacant | DEQ Public Information Specialist | (406) 438-2446 | |
Roger Hoogerheide | EPA Project Manager | Hoogerheide.Roger@epa.gov | (406) 457-5031 |
Clark Fork River Operable Unit
Annual Monitoring Reports
Phase 3 and 4 Documents and Plans
Phase 3 and 4 Draft Preliminary Design Report
Draft Data Summary Report May 2015
Phase 3 and 4 Appendix C, Part One
Phase 3 and 4 Appendix C, Part Two
Other Documents
Strategic Plan Response to Comments
Strategic Plan with Appendices October 2023
2017 Community Involvement Plan- Summary
2017 Community Involvement Plan- Full Document
2010 to 2017 Weed Control Summary Report
Explanation of Significant Difference June 2015
2008 Clark Fork River Consent Decree
2004 Record of Decision
Part 3: Responsiveness Summary
Part 4: Acronyms, Abbreviations & References
Appendix A: Indentification & Description of Applicable or Relevant & Appropriate Requirements
Appendix B: Streambank Stabilization Design Consideration & Examples
Appendix C: BMPs & Riparian Management Plan Considerations
Appendix D: Weed Prevention & Management Planning Information
Appendix E: Grant-Kohrs Ranch National Historic Site
Appendix F: Concurrence Letter from the State of Montana
The heavy metals (Cadmium, Copper, Zinc, and Lead) and arsenic in the Clark Fork River are from historic mining, milling and smelting processes linked to the Anaconda Company operations in Butte and Anaconda. The majority of the cleanup will occur along a 43-mile stretch of the river from Warm Springs in Anaconda/Deer Lodge County downstream to Garrison in Powell County. This is known as “Reach A.”
The Clark Fork River Operable Unit (CFR OU) is part of the Milltown Reservoir/Clark Fork River Superfund Site. The CFR OU includes the Clark Fork River from its headwaters near Warm Springs Creek to Milltown Reservoir, just east of Missoula.The primary sources of contamination are tailings mixed with soil in the streambanks and historic floodplain. These sources threaten human health and animal and plant life. The 2004 Record of Decision describes the cleanup approach, or Selected Remedy. In addition to the ROD, the NRDP developed a Restoration Plan to expedite the recovery time for injured aquatic and terrestrial resources in and along the Clark Fork River. To the extent practicable, the Restoration Plan will be combined with the Remedy to maximize the use of resources. The 2004 Record of Decision describes the cleanup approach, or Selected Remedy.
In 2008, 25 years after the state sued the Atlantic Richfield Co. for damage to natural resources, a settlement was reached and a federal judge signed the consent decree. The state received $123 million from ARCO for cleanup and restoration of mining pollution in the Clark Fork River Operable Unit.
The Montana Department of Environmental Quality (DEQ) and Montana Department of Justice, Natural Resource Damage Program (NRDP), with additional oversight from the U.S. Environmental Protection Agency (EPA) and National Parks Service (NPS) (for cleanup activities at the Grant-Kohrs Ranch operated by NPS) work collaboratively to design the remediation and restoration work.
In addition to the ROD, the NRDP developed a Restoration Plan to expedite the recovery time for injured aquatic and terrestrial resources in and along the Clark Fork River. To the extent practicable, the Restoration Plan will be combined with the Remedy to maximize the use of resources.
Click to subscribe for email updates for the Clark Fork River site: Email Updates
Name | Position | Phone Number | |
---|---|---|---|
Logan Dudding |
DEQ Project Manager |
406-444-6407 |
|
Jessica Banaszak |
DEQ Project Manager |
406-444-4158 |
|
Nolan Lister |
Public Information Specialist |
406-444-6469 |
|
Libby Asbestos
Libby Asbestos Site Overview and Updates
Federal Superfund sites in and around Libby, Montana include the Libby Asbestos site and the Libby Groundwater site. The Libby Asbestos Site is located in Libby and Troy in Lincoln County (see figure below). In the early 1920s, the Zonolite Company began vermiculite ore mining operations in Libby. Vermiculite from the Libby mine, bought by W.R. Grace in 1963, was contaminated with a toxic and highly friable form of asbestos called tremolite-actinolite series asbestos (often called Libby Amphibole asbestos or “LA”). The site has been divided into eight Operable Units (OU), as shown in the table below, to facilitate addressing contamination issues.
Operable Unit | Description | Status |
---|---|---|
OU1 |
Riverfront Part (former Export Plant) |
Remedial action complete. O&M ongoing. Partial deletion in 2020. |
OU2 |
Former Screening Plant |
Remedial action complete. O&M ongoing. Partial deletion in 2019. |
OU3 |
Former W.R. Grace Mine |
Remedial Investigation/Feasibility Study underway. |
OU4 |
Residential/Commercial properties in Libby |
Remedial Action Complete. O&M Ongoing |
OU5 |
Lincoln County Port Authority (former Stimson Lumber Mill) |
Remedial action complete. O&M ongoing. Partial Deletion 2024 |
OU6 |
BNSF Railroad Corridor |
Remedial Action Complete. O&M Ongoing. Partial Deletion 2022. |
OU7 |
Residential/commercial properties in Libby |
Remedial Action Complete. O&M Ongoing. |
OU8 |
Highways/Roadways |
Remedial Action Complete. O&M Ongoing. Partial Deletion 2021. |
About LASOC
In 2017, the 65th Montana Legislature passed Senate Bill 315, which was signed into law by Governor Bullock and established a Libby Asbestos Superfund Advisory Team attached to DEQ for administrative purposes. The Advisory Team was created to enhance communication with stakeholders. In addition, the Advisory Team advises DEQ on administration of the Libby Asbestos Cleanup Trust Fund and operation and maintenance accounts. The bill also established a full-time employee as the Libby Asbestos Superfund Liaison who will perform duties recommended by the team and facilitate the required quarterly Advisory Team meetings.
Subject to appropriation by the Legislature, money deposited in a state special revenue account must be used to fund cleanup and long-term operation and maintenance costs at the Libby Asbestos Superfund Site, and administrative costs of the Advisory Team and Libby Asbestos Superfund Liaison.
Libby Asbestos Superfund Oversight Committee Members
-
Commissioner, Brent Teske: (406) 283- 2317, bteske@libby.org
-
Director of the Department of Environmental Quality, Sonja Nowakowski: (406) 444-2544, sonja.nowakowski@mt.gov
-
Citizen of Lincoln County, George Jamison: (406) 293-8567, gjamison@libby.org
-
One member of the Montana House of Representatives, Rep. Steve Gunderson: (406) 334-4370, steve.gunderson@legmt.gov
-
One member of the Montana Senate, Sen. Mike Cuffe: (406) 293-1247 or (406) 889-5777, mcuffe@interbel.net and mike.cuffe@legmt.gov
Legislation
LASOC Final Bylaws February 2020
LASOC Final Bylaws Amended December 2021
Upcoming Oversight Committee Meeting Information
Conference ID Number: 127-269-949
Agendas and Meeting Materials
December 9, 2024 Oversight Committee Meeting Agenda
- LASOC Budget Report September 2024
- LASOC O&M Support of Property Owners
- Draft June 10, 2024 Meeting Minutes
September 23, 2024 Oversight Committee Meeting Agenda
- LASOC Budget Report September 2024
- Draft June 10, 2024 Meeting Minutes
- LASOC O&M Support to Property Owners
June 10, 2024 Oversight Committee Meeting Agenda
- LASOC Budget Report
- Draft March 4, 2024 Meeting Minutes
- DRAFT LASOC O&M Support of Property Owners Report
March 4, 2024 Oversight Committee Meeting Agenda
- LASOC Budget Report
- Draft December 19, 2024 Meeting Minutes
- LASOC O&M Support to Property Owners Report, January 2024
- REDLINED- Draft LASOC Support of Property Owners Report with Jan 2024 Updates
December 19, 2023 Oversight Committee Meeting Agenda
- Draft September 21, 2023 Meeting Minutes
- Updated Draft LASOC O&M Support to Property Owners Report December 2023
- LASOC Budget Report December 2023
September 21, 2023 Oversight Committee Meeting Agenda
- Draft June 22 Minutes
- Final LASOC Budget Report September 2023
- LASOC O&M Support to Property Owners Report September 2023
- 134 Parmenter Creek Rd
- 39265 HWY 2
- DEQ Libby Funding Policy Memo
- Draft LASOC DEQ Reimbursement Statement for Property Owners
- DRAFT March 9 Minutes
- Final LASOC Budget Report June Meeting
- Draft LASOC OM Support to Property Owners Report_June 2023
- Draft Final ECQ 2023 LASOC Annual Report
- 3274 FTM SOW and Bids (NOPEC)
- LASOC September 2022 Draft Minutes
- LASOC Budget Report December 2022
- NOEC-154 Paulines Way Bid
- Draft LASOC O&M Support to Property Owners Report December 2022
September 29, 2022 Oversight Committee Meeting Agenda
- June 2022 Meeting Minutes
- LASOC Budget 2022 Report
- 100 Manor Drive
- DEQ Hufford Decision
- LASOC Hufford Recommendation
- LASOC O&M Support to Property Owners
- Draft Revised LASOC Budget Report
- EQC 2022 LASOC Annual Report
- LASOC MOA
- Libby Asbestos Response Letter to Lincoln County
- Lincoln County O&M Funds Letter
June 01, 2022 Oversight Committee Meeting Agenda
- Draft LASOC March 2022 Minutes
- LASOC Budget Report June 1, 2022
- 42162 US HWY 2
- Refusal LASOC Request
- Draft LASOC O&M Support to Property Owners Report
- Draft EQC 2022 LASOC Annual Report
March 14, 2022 Oversight Committee Meeting Agenda
- Draft Analyses of Sitewide Activities
- Draft LASOC O&M Support of Property Owners Report
- LASOC Budget Report February 28, 2022
December 13, 2021 Oversight Committee Meeting Agenda
- LASOC Budget Report October 2021
- Draft LASOC Bylaws Amendment 1
- Proposed LASOC Subcommittee-Analyses of Sitewide Activities
- Proposed LASOC Subcommittee-Support of Property Owners
August 19, 2021 Oversight Committee Meeting Agenda
- EQC 2021 LASOC Final Annual Report
- LASOC Budget Report August 2021
- Libby Budget Overview Document and Spreadsheet
- Libby Bylaws Amendment Draft 1
- Budget Questions
June 22, 2021 Oversight Committee Meeting Agenda
- Libby Budget Overview
- Libby Budget Overview Detail
- Budget Comments
- MOA Signed ARP
- MT DEQ V-96841701-6
- Weston TO 03
- Draft EQC LASOC Annual Report June 2021
March 12, 2021 Oversight Committee Meeting Agenda
December 17, 2020 Oversight Committee Meeting Agenda
- DEQ Funding Decisions on Reimbursements for Property Owners
- Options for Making Recommendations to DEQ for Reimbursement Requests
- Libby Budget Overview, December 2020
September 24, 2020 Oversight Committee Meeting Agenda
- Libby Budget Overview September 2020
- Summary for Property Owner Costs Sept 2020
- DEQ Libby Funding Policy Memo
- Recommendation for Funding Property Owner Costs
May 26, 2020 Oversight Committee Meeting Agenda
- Reimbursement Flowchart Version 7
- Motion for State O&M Funding, LASOC
- Investigation Sampling Flowchart Version 5
- DRAFT DEQ Libby Funding Policy Memo
- Estimate of Cost, Unfunded Categories
- EQC Annual Report June 2020 LASOC
February 10, 2020 Oversight Committee Meeting Agenda
- Budget Overview January 2020
- 08-12-2019 Outstanding Settlement Dollars Request, signed
- BOH Motion Re: Public Comment Periods 11-13-2019
- DEQ Response to BOH Motion
- EPA Response to BOH Motion
- EPA Use of Settlement Funds on O&M Specific Items
- DEQ Response to EPA Use of Settlement Funds Letter
- Estimate of Cost-Unfunded Categories
- ICIAP Comments-Rep. Steve Gunderson 12-09-2019
- ICIAP Comments-Senator Mike Cuffe 12-09-2019
- LASOC Draft Bylaws 1-31-2020
- O&M Position Statement 1-2018
December 17, 2019 Oversight Committee Meeting Agenda
- Budget Overview December 2019
- LASOC Draft Bylaws with Questions
- Reimbursement Flowchart
- Funding Matrix
- Motion Re: Public Comment Periods
September 19, 2019 Oversight Committee Meeting
- Budget Overview September 2019
- Guiding Principles -September 2019
- EPA Response Letter - June 2019
- LASOC Bylaws - Draft
August 12, 2019 Oversight Committee Meeting
- Initial Lincoln County Draft_For Discussion Only_LASOC Guiding Principles Document_08092019
- Outstanding Settlement Dollar Request Signed_August 12, 2019
August 2, 2019 Oversight Committee Meeting
June 24, 2019 Libby Oversight Committee Meeting
- Budget Overview for June 2019
- EQC Annual Report June 2019
- Memo Scope of Work Considerations for Lincoln Co MOA
- Lincoln Co Letter to Doug Benevento O&M Planning Activities
- EPA Letter to Commissioner Peck OU4 and OU7
- DEQ Letter to Stan Christenson OU4 and OU7
- EPA Letter to Tom Stoops OU4 and OU7
- O&M Position Statement January 2018
- Lincoln Co Letter to Stan Christenson
- Lincoln County Letter Critical Transition Issues
- Office of Governor Letter to Doug Benevento
- EPA Letter to Honorable Steve Bullock
- Outstanding Settlement Dollars Request_Draft
March 26, 2019 Libby Advisory Team Meeting Agenda
December 19, 2018 Libby Advisory Team Meeting Agenda
September 7, 2018 Libby Advisory Team Meeting Agenda
June 28, 2018 Libby Advisory Team Meeting Agenda
- ARP Property O & M Process
- Budget Overview for June 2018
- Libby Asbestos Fund Restrictions
- OU5 Briefing Paper
March 8, 2018 Libby Advisory Team Meeting Agenda
- O & M Position Statement January 2018 Signed
- Recruitment Strategy, Updated
- Budget Overview, March 2018
- LibbyOU4_OU7NextStepsHandout
- IC Report of Recommendations
- Board of Health Re: Public Health Emergency_Signed
December 18, 2017 Libby Advisory Team Meeting Agenda
September 21, 2017 Libby Advisory Team Meeting
Meeting Minutes
September 23, 2024 Meeting Minutes Approved
June 10, 2024 Meeting Minutes Approved
March 4, 2024 Meeting Minutes Approved
December 19, 2024 Meeting Minutes Approved
September 21, 2023 Meeting Minutes Approved
June 22, 2023 Meeting Minutes Approved
March 9, 2023 Meeting Minutes Approved
December 15, 2022 Meeting Minutes Approved
September 29, 2022 Meeting Minutes Approved
June 1, 2022 Meeting Minutes Approved
March 14, 2022 Meeting Minutes Approved
December 13, 2021 Meeting Minutes Approved
August 19, 2021 Meeting Minutes Approved
June 22, 2021 Meeting Minutes Approved
March 12, 2021 Meeting Minutes Approved
December 17, 2020 Meeting Minutes Approved
September 24, 2020 Meeting Minutes Approved
May 26, 2020 Meeting Minutes Approved
February 10, 2020 Meeting Minutes Approved
December 17, 2019 Meeting Minutes Approved
September 19, 2019 Meeting Minutes Approved
August 12, 2019 Meeting Minutes Approved
August 2, 2019 Meeting Minutes Approved
June 24, 2019 Meeting Minutes Approved
March 26, 2019 Meeting Minutes Approved
December 19, 2018 Meeting Minutes Approved
September 7, 2018 Meeting Minutes Approved
June 28, 2018 Final Meeting Minutes Approved
March 8, 2018 Meeting Minutes Approved
December 18, 2017 Meeting Minutes Approved
September 21, 2017 Meeting Minutes Approved
Meeting Memos
September 29, 2020 Interim Recommendations for LASOC
For More Information:
Melody Wunderlin | Section Supervisor | (406) 444-6456 |
Nolan Lister | Public Information Specialist | (406) 444-6469 |
These links contain general asbestos information:
Name | Position | Phone Number | |
---|---|---|---|
Melody Wunderlin |
DEQ Project Officer |
(406) 444-6456 |
|
Nolan Lister |
DEQ Public Information Specialist |
nolan.lister@mt.gov |
(406) 438-6469 |
Amanda Harcourt |
Lincoln County Asbestos Resource Program |
(406) 283-2445 |
|
Beth Archer |
EPA Community Involvement Coordinator |
(303) 312-6611 |
|
Dania Zinner |
EPA Remedial Project Manager |
(303) 312-7122 |
Montana Pole and Treating Plant
DEQ released the final Explanation of Significant Differences (ESD) for the Montana Pole. See documents section below for both the final ESD and responsiveness summary. The ESD proposes changes to the original cleanup plan to make the site more protective of human health and the environment. Now that the ESD is complete and approved by the Environmental Protection Agency (EPA), construction can begin this summer on the final cleanup for the south side of the site allowing for future redevelopment.
Construction for remediation cleanup will include placing the treated soils in an onsite designated capped area called a Corrective Action Management Unit (CAMU). The new cleanup levels will allow for commercial and industrial redevelopment for 27 acres of the site. The remaining 9 acres is the site of the CAMU, which will be comprised of the treated soils area and additional soils removed to achieve the new cleanup levels. The operation and maintenance of the CAMU will be overseen by the state to ensure protectiveness and will have regular Five Year Reviews. Five Year Reviews are a standard process required whenever contamination is safely left onsite. The reviews make sure the site remains protective.
Click to subscribe for email updates for the MT Pole site: Email Updates
5-Year Review |
Date |
Fifth 5-Year Review | June 2022 |
Fourth 5-Year Review | April 2017 |
Third 5-Year Review | June 2011 |
Second 5-Year Review | June 2006 |
First 5-Year Review | June 2001 |
Annual Reports |
Date |
2015 Final MPTP Annual Report | March 2016 |
2016 Final MPTP Annual Report | April 2017 |
2017 Final MPTP Annual Report | August 2018 |
2018 Final MPTP Annual Report | March 2019 |
2019 Final MPTP Annual Report | March 2020 |
2020 Final MPTP Annual Report | April 2021 |
Fact Sheets |
---|
March 2021 |
October 2020 |
April 2016 |
October 2014 |
June 2013 |
March 2011 |
April 2010 |
Newsletters |
February 2023 |
April 2022 |
Former Log Storage Area | Aerial view of southern portion of the site | Land treatment unit. |
Name | Position | Phone Number | |
---|---|---|---|
Jacob Wheeling |
DEQ Project Manager |
(406) 444-6420 |
|
Allie Archer |
EPA Project Manager |
(406) 457-5033 |
|
Nolan Lister |
DEQ Public Information Specialist |
(406) 444-6469 |
|
Silver Bow Creek / Butte Area Stream Side Tailings
Interactive Story Map
The cleanup of Silver Bow Creek has been ongoing since 1999 as part of a Superfund remedial action being coordinated by the Montana Department of Environmental Quality (DEQ) in consultation with the U.S. Environmental Protection Agency (EPA). In 2000, the Natural Resource Damage Program (NRDP) of the Montana Department of Justice formed a partnership with DEQ, bringing a restoration component to the project that goes beyond remediation required under Superfund. Provided below is a brief history of the project, updates regarding the current status of the project, and descriptions of activities planned in future years.
Silver Bow Creek extends from Butte approximately 23 miles to the Warm Springs Ponds, a water treatment facility located at the headwaters of the Clark Fork River (see corridor map). Since the late 1800s, tailings and other mine wastes containing elevated concentrations of metals have been discharged to or otherwise entered Silver Bow Creek. These toxic discharges impacted the stream and floodplain with heavy metals and virtually eliminated aquatic life in the stream. Tailings deposited in the floodplain are toxic to plants and have resulted in a floodplain that is largely devoid of vegetation and is generally incapable of supporting wildlife. In 1983, EPA listed the Silver Bow Creek/Butte area as one of multiple Superfund sites in the Upper Clark Fork River Basin. The agency later designated the approximately 23 stream miles of streamside tailings along Silver Bow Creek as an operable unit (OU) within this overall Superfund site. The Streamside Tailings Operable Unit (SSTOU) has become one of the areas of focus for Superfund cleanup in the Butte area. Initially, EPA named ARCO as the primary party responsible for remediation of the SSTOU and other Superfund sites in the Upper Clark Fork Basin through its acquisition of the Anaconda Company. EPA and DEQ issued a Record of Decision (ROD) for the site in November 1995 that identifies the final site remedy and the agencies' rationale for selecting that remedy. The major remedial action that resulted from issuance of the ROD is excavation of tailings and related impacted soils from the floodplain of Silver Bow Creek and reconstruction of the stream channel and floodplain. For planning purposes, the SSTOU was divided into four subareas, each with a distinct geologic and geographic character.
The Natural Resources Damage Program (NRDP) Connection. In a 1999 state, federal and tribal settlement, ARCO agreed to pay $215 million to the State to resolve certain claims. From the settlement amount, $80 million plus interest was set aside for DEQ and EPA to implement the remedy for Silver Bow Creek. Some of the remaining amount is being used to enhance the cleanup of Silver Bow Creek through various habitat improvements and restoration actions. DEQ and EPA are coordinating the cleanup of the Silver Bow Creek remedy with NRDP.
After 16 years of cleanup, the Silver Bow Creek/Streamside Tailings cleanup reached completion in summer 2015.
Cleanup consisted of excavation of tailings (mine waste containing heavy metals) and related impacted soils from the floodplain of Silver Bow Creek, and the reconstruction of the stream channel and floodplain, and total revegetation. 5.8 million cubic yards of tailings were hauled, or enough to fill Grizzly Stadium to the brim 21 times. The contaminated waste was hauled to Opportunity Ponds. Approximately 1,550 acres along Silver Bow Creek have been remediated and restored.
Fish surveys show that populations of Westslope cutthroat, brook trout, sculpins, and suckers have reestablished in the creek. Shrub and tree planting activities have enhanced wildlife habitat, along with a DEQ-implemented weed management program. Sightings of over 100 bird species, including bald eagles, osprey, swans, blue heron, and sandhill crane are common in the floodplain and wetland areas, as well as deer, elk, moose, beaver, muskrats, and mink.
DEQ will implement a 'final pass' cleanup before subareas are transitioned into operations and maintenance status. The final pass will address very small deposits of remaining remnant tailings-impacted soils to improve and enhance the remediation as a whole.
Documents & Reports Name | Date |
---|---|
Final Monitoring Report 2019 | June 2020 |
Final Monitoring Report 2018 | July 2019 |
Final Monitoring Report 2017 | August 2018 |
Final Monitoring Report 2016 | July 2017 |
Final Monitoring Report 2015 | October 2016 |
Final Monitoring Report 2014 | December 2015 |
Silver Bow Creek Overview Update Map | March 2012 |
Interim Comprehensive Long-Term Monitoring Plan | 2010 |
Interim Comprehensive Long-Term Monitoring Plan | 2009 |
Restoration Economy | September 2009 |
The Silver Bow Creek Greenway | |
Corridor Map |
Ospray and its Fish Photo taken by Don MacGee. Summer of 2011 |
Young Angler, Rye Vincent Rye Vincent is holding an 18.5 inch cutthroat trout catch from Silver Bow Creek just below Miles Crossing bridge. Summer of 2010 |
The Mink Return This mink was seen along Silver Bow Creek in September 2009. Mink prey on fish so the presence of mink indicates a return of fish to the stream. |
Name | Position | Phone Number | |
---|---|---|---|
Logan Dudding |
DEQ Project Officer |
(406) 444-6407 |
|
Ken Champagne |
EPA Project Manager |
(406) 457-5025 |
|
Non-NPL Construction Sites
Black Pine Mine
PHOTO needs to be transferred
The Black Pine Mine (BPM/Site) is an inactive silver mine located 10 miles northwest of Philipsburg in Granite County. The BPM complex includes 1,056 acres of patented mining claims and 150 unpatented lode claims. It is surrounded by lands administered by the US Forest Service. Approximately 400,000 CY of metals-impacted wastes are estimated to be present at, and down gradient of the Site. The impacted wastes include waste rock, tailings, and metals impacted soils and sediments.
The BPM is one of five sites in Montana that was owned and operated by ASARCO, until their bankruptcy filing in August 2005. In December 2009, $17.3 million was allocated to the BPM for environmental actions at the Site. DEQ was appointed as the lead agency for the reclamation. These funds are being managed by the Montana Environmental Trust Group, LLC (METG), Trustee for the Montana Environmental Custodial Trust.
DEQ performed a site characterization to investigate the nature and extent of contamination associated with mining and milling waste at the Site. Based on the results of the site characterization, reclamation alternatives are being evaluated to address human health and ecological risk.
Attention Contractors
To be considered during an invitation for bid, a contractor must meet several criteria, including but not limited to being bonded and insured, a registered contractor with the State of Montana and trained (40 hours) in emergency hazardous waste operations (HAZWOPER). The DEQ will develop designs for various stages of the work. When the design is complete, the project will be put out for construction bid on the DEQ website at www.deq.mt.gov. The DEQ will respond to questions and hold a pre-bid conference. Bids are sealed and opened at once in public. The DEQ selects the lowest responsible bidder.
Document | Date |
---|---|
Site Cleanup Update | October 2017 |
Final Conceptual Repository Design | August 2014 |
June 2014 |
|
Draft Conceptual Repository Design Technical Memorandum | June 2014 |
Repository Conceptual Design Plan Set | June 2014 |
December 2013 |
|
May 2012 |
|
August 2010 |
Name | Position | Phone Number | |
---|---|---|---|
Bob Flesher |
DEQ Project Manager |
406-444-6492 |
|
Sonny Thornborrow |
Project Manager |
406-494-0202 |
|
Stimson-Bonner Mill PCB
The Bonner Mill Cooling Pond cleanup project is located in Bonner, Montana, along the Blackfoot River. In the early 1880s, the first logs were cut at the Bonner mill site and shipped to the mining operations in Butte. Over time, the Bonner mill site owners built and operated a “cooling pond,” which actually extended out into the Blackfoot River. In 2006, DEQ discovered contaminants (PCB) in the sediments of the cooling pond. The Department of Natural Resources & Conservation determined that because of the removal of the Bonner and Milltown dams immediately downstream from the cooling pond area, the berm of the cooling pond would fail during the next 100-year high flow flood, washing the PCBs downstream. Working with DEQ, Stimson Lumber entered into an Administrative Order of Consent in 2010 to remove the PCB contaminated areas threatening the Blackfoot River. Between September 2010 and April 2016, contaminated soils and debris was removed from the site and shipped to landills or an on-site repository; the river was restored and no longer does a threat from PCBs exist from areas it once did. This webpage provides links to public fact sheets and updates throughout the life of the project.
No public input received on a Draft Plan to Remove Wastes at the Bonner Mill Site Repository located in Missoula, MT
The Montana Department of Environmental Quality (DEQ) requested public input on a draft plan submitted by Bonner Property Development, the current landowner of the site, to remove waste at the Bonner Mill Site Repository and dispose of the waste at the Republic Landfill located in Missoula, MT. Currently, the repository is performing as designed and remains protective of human health and the environment. DEQ is not requiring any party to remove or alter the repository. DEQ has not approved any amendment or modification to the current restrictive covenants at the site. Public input was accepted until 5:00 p.m. on October 9, 2020. DEQ received no public input.
With the close of a request for public input, DEQ is currently reviewing the plan. DEQ’s review of the submitted draft plan will ensure that the proposed work will not conflict with ongoing work at the facility and that the work conducted will not spread, worsen, or otherwise exacerbate the PCB contamination. DEQ will review the plan to guarantee that all other relevant factors are considered for protectiveness of human health and the environment and that wastes are disposed of in a permitted landfill. If appropriate after such on-going review, DEQ may require revisions and additional information or approve a detailed work plan outlining the proposed work.
The draft plan documents are part of the administrative record. Site documents may be requested here: https://montanadeq.govqa.us/WEBAPP/_rs/(S(iv3hbh02ft3pfjbr2m144mfq))/supporthome.aspx
Name | Position | Phone Number | |
---|---|---|---|
Vacant |
DEQ Project Manager |
|
406-444-6569 |
Nolan Lister |
Public Information Specialist |
406-444-6469 |
|
Upper Blackfoot Mining Complex
Site Overview
The Upper Blackfoot Mining Complex (UBMC) is a state superfund facility located about 15 miles east of Lincoln. Seeps from the tailings and waste rock dumps along with acid mine drainage from old adits have contaminated surface water, sediments, soils and groundwater. Additional contamination exists due to the 1975 dam failure that washed metals-laden tailings down the Beartrap Creek drainage and into the upper Blackfoot River.
DEQ has led cleanup efforts in coordination with the United States Forest Service (USFS) and Montana Natural Resource Damage Program (NRDP) over the past several years. The primary goal of the cleanup is to remove approximately 1 million cubic yards of tailings and mine waste to protect human health and the environment. This protection will be accomplished by minimizing direct contact with contaminants and limiting migration and mobility of contaminants within the environment.
Reclamation Nears Completion on Upper Blackfoot Mining Complex in Lewis & Clark County
Reclamation work is nearing completion at the Upper Blackfoot Mining Complex (UBMC), a State Superfund site located in Lewis & Clark County east of Lincoln, Mont.
The reclamation work has been a coordinated effort of the Department of Environmental Quality (DEQ), Department of Justice – Natural Resource Damage Program (NRDP) and United States Forest Service (Forest Service).
Historical mining practices contaminated the floodplains and waterways downstream of the Mike Horse Dam. The dam was built in 1941 to contain mine tailings but failed in 1975, flushing more than 200,000 cubic yards of mine tailings downstream for almost 10 miles and into the Blackfoot River. Required restoration and reclamation work included removal of the tailings dam and contaminated floodplain waste, as well as stream channel construction and floodplain restoration.
The cleanup removed approximately 1 million cubic yards of tailings and mine waste that had contaminated streams and the adjacent floodplains and made survival difficult for aquatic life, including fish. The contaminated material was removed from the banks and floodplain of the Blackfoot River and its tributaries, and encapsulated in a nearby repository. Water quality has returned to healthy levels following the reclamation and restoration of the site.
“This site is a great example of agencies working together to clean up pollution left by historic mining,” said Project Officer Dave Bowers from DEQ. “This unique piece of Montana can now be used by everyone to enjoy the clean river, trails and wildlife. Most importantly, the site is protective of human health and the environment.”
Restoration was completed on Mike Horse Creek, Beartrap Creek and Blackfoot River stream channels and adjacent floodplains. Fish are already populating the newly constructed stream channels.
“Seeing the restored streams teeming with life as clean, cold water flows from high on the continental divide is something we can all be proud of,” said Restoration Project Manager Beau Downing from NRDP. “I believe I speak for everyone involved with the project in saying that the outcome has far exceeded our expectations. Working with DEQ, the USFS, our project partners, and the contractors to complete the project has been a highlight of my career.”
Funding for the cleanup came from a $39 million settlement with Atlantic Richfield Co. and ASARCO, LLC—companies that came to own much of the historic mining district.
While a majority of the work is done, DEQ and the Forest Service may still have work to do in the areas outside the floodplains depending on the availability of alternative funding sources. Smaller areas disturbed by past exploration and mining practices were identified in the Record of Decision and need to undergo “design level” investigations. These investigations will determine the exact actions, if any, that need to be taken at each site. Depending on the outcomes of the investigations, possible actions could range from no action at all to complete removal.
“The work completed at the site is a true demonstration of multiple agencies working cooperatively together for the betterment of the environment in Montana,” said Steve Opp, on-scene coordinator for the Helena-Lewis and Clark National Forest. “The project partners have committed to long-term monitoring of the site that will last several years to measure the effectiveness of the clean-up and restoration.”
The site is now open for recreational use. The nonprofit Blackfoot Challenge is working on a self-guided tour that will feature information kiosks located throughout the UBMC. The kiosks will include information panels covering topics such as unique plants and wildlife as well as a history of the mining that occurred in the area.
The Upper Blackfoot Mining Complex (UBMC) is an inactive mining district more than 50 acres in size and located 15 miles east of Lincoln, Montana. American Smelting and Refining Company (Asarco) constructed the UBMC water treatment plant in 2008 and began operation in January 2009. The plant collects discharge from two mine adits and two seeps, treats the waters with chemicals and a ceramic membrane filter system, and then discharges the water into the Upper Blackfoot River. The primary metals that are removed are cadmium, copper, iron, lead, manganese and zinc. As part of the Asarco bankruptcy, Asarco funded a Trust to operate the water treatment plant with State of Montana oversight.
If you have any questions concerning water treatment plant operations, please direct your inquiries to:
Robert Roll
Remediation Division
1225 Cedar Street, Helena, Montana 59602
406-444-6438
rroll@mt.gov
NEWSLETTERS
DEQ, in coordination with the USFS and NRDP, puts out the Mike Horse Messenger, the newsletter for the Upper Blackfoot Mining Complex. It is generally published twice a year, before and after the field season, to keep interested parties informed of progress at the UBMC.
If you would like to receive the Mike Horse Messenger or any other mailings on the UBMC from DEQ, please to subscribe for email updates for the UBMC site: Email Updates
News Articles |
---|
Blackfoot Valley Dispatch (Article):'Restoring life to the UBMC' |
Blackfoot Valley Dispatch (Article):Work on UBMC cleanup set to resume this summer, public meeting planned |
Blackfoot Valley Dispatch (Article): 'Watershed Moments' |
Blackfoot Valley Dispatch (Article): 'Quake |
Montana Council of Trout Unlimited (Article): 'Good News for the Big Blackfoot' |
Blackfoot Valley Dispatch(Article):'DEQ releases record of decision for final cleanup of Upper Blackfoot Mining Complex' |
Blackfoot Valley Dispatch(Article):'DEQ, USFS, detail plan for cleaning up remaining UBMC contamination' |
Blackfoot Valley Dispatch (Article): Cleanup Moves Ahead |
Blackfoot Valley Dispatch(Article): 'Last of the Blue Goo' |
Blackfoot Valley Dispatch (Article):'Historic Dam Progress at the Mike Horse' |
Governor's Visit |
---|
Decision Documents | ||
Document | Description | Year Published |
Record of Decision | The Record of Decision identifies the final remedy for completing cleanup activities on non-federla lands at the UBMC site. | 2016 |
Final Feasibility Study Report | The Feasibility Study was prepared to develop, screen, and evaluate remedial action alternatives for the UBMC. | 2016 |
Final Human Health Risk Assessment | Presents the findings of the baseline human health risk assessment conducted on the UBMC. | 2014 |
Final Eco-Risk Assessment | Explains how the UBMC contamination in soil, stream sediment, and surface water affects the environment | 2013 |
Final Remedial Investigation Report | Soil, sediment, surface water, groundwater, and biological data collected in 2007, 2008, and 2011 to determine the extent of contamination in the UBMC | 2013 |
2012 Repository Decision (USFS website) | Amendment to the 2007 USFS decision changing the repository location for the Mike Horse waste | 2012 |
Comparative study of locations for a repository for the Mike Horse waste | 2011 | |
2007 UBMC Action Memorandum | USFS decision on removal in the UBMC, including the Mike Horse Dam | 2007 |
Monitoring Reports | ||
Document | Description | Year Published |
2012 Mining Area Monitoring Reports | Data collected from surface water, groundwater, and stream sediments to establish existing conditions before cleanup | 2013 |
2012 Section 35 Monitoring Report | Data collected from surface water, groundwater, and stream sediments to establish existing condition before the repository is built | 2013 |
2011 Mining Area Monitoring Report | Data collected from surface water, groundwater, and stream sediments to establish existing condition before cleanup | 2012 |
2011 Section 35 Monitoring Report | Data collected from surface and groundwater to establish existing condition before the repository is built | 2012 |
2010 Mining Area Monitoring Report | Data collected from surface water, groundwater, and stream sediments to establish existing condition before cleanup | 2012 |
2009 Mining Area Monitoring Report |
Data collected from surface water, groundwater, and stream sediments to establish existing condition before cleanup | 2010 |
Construction Investigation and Documents | ||
Document | Description | Year Published |
Data collected to determine extent of removal of mine waste from the mining area and ensure proper placement in the repository | 2013 | |
2012 Repository Design-Level Investigation | Data collected to determine proper design of the repository | 2013 |
Water Treatment Plant | ||
Document | Description |
Year
Published
|
Evaluation of Alternatives for Optimization of the UBMC WTP | Investigation of alternatives to optimize the WTP for greater efficiency and cost savings | 2019 |
Name | Position | Phone Number | |
---|---|---|---|
Amber Nichols |
DEQ Project Manager |
(406) 444-6569 |
|
Nolan Lister |
DEQ Public Information Specialist |
(406) 444-6469 |
|
Beau Downing |
NRDP Restoration Project Manager |
(406) 444-0291 |
|
Steve Opp |
USFS On-Scene Coordinator |
(406) 495-3716 |