MONTANA WIND WORKING GROUP January
24, 2008
Larry Flowers presented an update
of Wind Powering America activities including the projected implications for Montana from reaching a
20% wind power goal nationally. Achievement
of the goal targets 2030. The Power
Point presentation can be found at http://www.eere.energy.gov/windandhydro/windpoweringamerica/pdfs/wpa/wpa_update.pdf. Larry also reported progress toward
establishing a Wind Application Center
at Montana State University. Larry indicated he has had a number of
productive meetings recently with representatives of various schools of
engineering and school administrators in Bozeman. The Wind
Application Center
is designed to train wind power professionals who obtain practical, applied
experience as part of the Montana
State University
undergraduate engineering curriculum.
The Wind Application
Center would also support the Wind for
Schools initiative within Montana. The wind industry strongly supports this
effort since it is hiring at unprecedented levels and needs well trained
professionals. Larry reported that the
Board of Directors of the American Wind Energy Association spent much of its
annual meeting discussing and encouraging this effort. Larry noted that, ironically, the weak dollar
has spawned new foreign investment in the United States for wind turbine,
tower, blades and parts manufacturing.
Mike Cashell – The transmission
system was built in a certain way which is how we find it. Bulk transmission developed where there was
hydro first and than thermal. Mike recounted
the move in Montana
to power markets and the return, through re-regulation, to vertically
integrated utility systems again. Within
Montana, 333MW
have been added to the system in the 2.5 years between 2005 and 2007. Currently, NorthWestern Energy is considering
two publicly announced proposals to add bulk transfer capacity to their
transmission network – upgrading the 500kv system by adding a new substation
and installing series capacitors and the Mountain States Transmission Intertie
500kv line, http://www.msti500kv.com/. MISTI – NorthWestern Energy is working on permitting
this 500kv line from Townsend into Idaho. There are a number of potential routing
options. Montana Alberta Tie Ltd. (MATL) – NorthWestern Energy has been working
with MATL to interconnect their 230kv line to the network. The necessary paperwork was filed with FERC in
December. Mike suggested consideration
should be given to overbuilding certain lines since significant economies of
scale can be captured. For example, it
only costs 17 percent more to build a 230kv line rather than 115kv line. The increases in transfer capacity are many
times greater. Mike reported that
NorthWestern Energy’s regulation costs are 4 times higher this year compared to
last year. In addition, NorthWestern
Energy has only been able to secure them under a one year contract. NorthWestern Energy’s integration resource
costs now exceed $100 million dollars and their regulation capacity requirement
has grown to plus or minus 60MW to 65MW.
Some of the attendees questioned what these costs might be for small
wind power projects. Colstrip 500kv
upgrade - NorthWestern Energy and its Colstrip partners have
had discussions about adding capacity to the Colstrip 500kv line through
the measures outlined above. The partners were quite
interested initially, but some of the partners backed away because they
felt coal-fired generation is out of favor and can not be purchased or
placed into rates in some of the larger western utility service
areas. The perceived lack of coal-fired transmission users was viewed as
detrimental to the project's fundamental economics. This reticence caused
discussions to stall, at least temporarily. Mike reported that while NorthWestern
had experienced starts and stops on the 500 kV upgrade with the other Colstrip
owners, it has never stopped pursuing it and still views the project as very
attractive. The other Colstrip owners have recently expressed renewed
interest so NorthWestern Energy is working with them again. Finally, Mike
indicated the Colstrip partners are discussing various ways to allocate the
potential transmission capacity that would result from the proposed upgrades to
the 500kv Colstrip line - nothing is set in stone at this point. Mike said there is an existing contract between
the partners which will need to be considered (Colstrip Transmission Agreement)
and may have an impact on the parties’ rights and obligations going
forward. Various allocation schemes have been discussed including
divvying up the increased transfer capacity based on each partner’s financial
support of the upgrades. Nothing final has been worked out yet.
Bill Rhoads and John Fitzpatrick
reported on NorthWestern’s announcement to construct, own and operate a natural
gas plant to regulate their loads and integrate wind projects - http://www.northwesternenergy.com/OurCompany/NewsCenter/displaynews.aspx?Page=Site_Selection_for_Proposed_Electric_Generation_Plant_Announced&article=6684&Item=20. The proposed natural gas plant would be
located near the Mill Creek Substation.
Bill and John noted that interconnection and transmission service cost
and availability is strongly influenced by location and NorthWestern Energy was
fortunate to have found the Mill Creek location.
Representatives of the Montana
Alberta Tie Limited (MATL) updated the Wind Working Group on its progress
toward obtaining all of the permits and approvals needed to build their proposed
230kv transmission line. MATL representatives
indicated that they would like to be able to build the proposed power line in
2008, but having construction pushed back another year would not doom it or
apparently any of the wind power developments tied to it. Construction \of the MATL 230kv transmission
line would represent a 10% increase in Montana’s
intertie capacity. Naturener is the only
specified shipper participating in the project.
Invenergy and Wind Hunter have subscribed but haven’t yet specified
project from which deliveries would be made to the line. MATL’s Power Point presentation can be
reviewed by clicking the following hypertext link. (DEQ should have the MATL Power Point on its
laptop.)
Peggy
Beltrone reported that she and Gary Siefert with the Idaho
National Energy Laboratory are working with officials at Malmstrom to resolve
potential impacts local wind projects might pose to the antiquated radar system
installed at the base.
Bill Pascoe indicated
NorthWestern Energy had announced at its last Transmission Advisory Committee
meeting that they would be willing to complete two economic planning studies
each year for free. Bill suggested this
was an opportunity the Montana Wind Working Group should explore. The Wind Working Group agreed requesting an
economic study to evaluate the transmission implications of future wind power
projects would be useful. The Wind
Working Group agreed to have interested members work together to develop and
submit an economic planning study proposal.
Bill reminded the Wind Working Group that the deadline for submitting
projects is February 29th which makes time critical. In fact, the Montana Wind Working Group did
submit an economic study request by the deadline.