Landfill Closure Review Sequence
- Pre-closure discussions begin.
- Landfill Closure Plan received by the Waste Management Section.
- Landfill Closure Plan reviewed by the Waste Management Section. During this step, more information may be requested in order to complete review process.
- The Waste Management Section notifies owner/operator in writing that Closure Plan has been approved or disapproved.
- Landfill owner/operator notifies the Waste Management Section (WMS) of intent to close.
- Upon completion of closure work, owner/operator notifies WMS in writing that landfill unit has been closed.
- The WMS places landfill in interim closure status and holds in abeyance any fees due until closure compliance is verified by WMS and/or a Professional Engineer (PE) has inspected and signed-off on closure work.
- Site required to be revegetated within one year of closure.
- Owner/operator surrenders solid waste management license to WMS.
- Owner/operator records a notation on deed to landfill property and notifies WMS.
- Landfill now closed, post-closure care begins
- Landfill file moved to "closed" section of files.