Federal Superfund Home

Note: An "X" designates a completed activity (e.g. "X" under the Remedial Investigation/Feasibility Study category means a Record of Decision has been issued for this operable unit). A number after an "X" or an "on-going" denotes the number of completed or on-going activities for that operable unit.

Federal Superfund Sites


Federal
Superfund Sites

Site assessment
(site-wide)

Interim cleanup
actions
Remedial
investigation/
feasibility
study


Record of
decision
Remedial
design/
remedial
action

Operation
and
maintenance
Sites Coordinated by DEQ
SILVER BOW CREEK            
  Warm Springs Ponds   X X  X(2)
 interim
X on-going
  Streamside Tailings X   X  X on-going on-going
  Rocker Treatment Plant   X X  X X on-going
  Mine Flooding   X X  X on-going on-going
  Priority Soils   X(8)
on-going(2)
X X negotiations  
  Active Mine Area            
  Westside Soils            
MONTANA POLE (BUTTE) X X(2) X  X on-going on-going
Sites Coordinated by EPA (links exit to EPA's web site)
ANACONDA X          
  Mill Creek     X  X X  X
  Flue Dust     X  X X on-going
  Arbiter Beryllium   X X   X on-going
  Old Works East Anaconda   X X  X X on-going
  Regional Water Waste Soils     X  X on-going on-going
  Smelter Hill     X   on-going  on-going
  Community Soils   X X  X on-going  
BARKER HUGHESVILLE X X on-going      
BASIN X          
  Basin Town     X  X X on-going
  Basin Watershed   X on-going      
BN SOMERS X X X  X X on-going
CARPENTER SNOW CREEK X X X on-going    
EAST HELENA SMELTER X          
  Remedial Soils     X on-going    
  Surface Soils Removal   on-going        
  Process Ponds & Fluids     X  X X Deferred to
RCRA
IDAHO POLE (BOZEMAN) X   X  X on-going on-going
LIBBY ASBESTOS X          
  Removal   on-going        
  Remedial     on-going      
  Troy OU     on-going      
LIBBY GROUND WATER X X X  X on-going on-going
  Buy Water Plan     X   X on-going
  Upper Aquifer and Soils     X   on-going  
  Lower Aquifer     X   X on-going
LOCKWOOD SOLVENT X X X  X negotiations   
MILLTOWN RESERVOIR X X        
  Water Supply     X  X X (2) on-going
  Reservoir Sediments     X  X on-going  
CLARK FORK RIVER     X  X on-going  
MOUAT (COLUMBUS) X X(3) X     on-going
UPPER TENMILE CREEK MINING AREA X X X X on-going  
TOTALS
  C=Completed
  OG=On-going
15 C
0 OG
16 C
3 OG
27 C
6 OG
20 C  12 C
2 neg.
12 OG
1 C
1 deferred
18 OG